Small Water System Consolidation with Sunnyslope Project - Invitation for Bids

Project Plans and Specifications
Please see the Plans & Specifications for the project in the links below.
Notice Inviting Bids & Specification PackageProject Plans PackageKey Dates
- MANDATORY pre-bid meeting and site walk on Wednesday, October 29, 2025 at 10:00 AM PST.
- Bids are due Thursday, November 20, 2025 at 3:00 PM PST.
Summary of Work
- New Water Mains - about 6.25 miles
- 3,570 LF of 18" water main
- 25,800 LF of 12" water main
- 440 LF of 8" water main
- 3,230 LF of 6" water main
- About 1.25 miles required as Horizontal Directional Drill
- About 2.85 miles as optional HDD or Open Trench
- About 1.6 miles required as Open Trench
- About 0.67 miles slip-lining inside existing pipe
- Jack & Bore under Hwy 25 at Quien Sabe Rd
- Rough grading portion of Fairview Corners for water line installation
- New Welded Steel Water Tank
- Rough & finish site grading & improvements
- Construct 275,000 gallon welded steel tank
- Coatings, cathodic protection, & piping
- Modifications to Existing Steel Tanks
- Modify existing 125,000 gallon bolted steel Foxhill tank piping, fittings, & appurtenances
- Modify existing 150,000 gallon welded steel Stonegate tank piping, fittings, & appurtenances
- Abandon Existing Wells
- Destroy Venture Estates well
- Disconnect from Tres Pinos well, but leave the well
- Disconnect Stonegate well from potable system and reconnect to nonpotable system
- Abandon Tres Pinos Tank
- Fully demolish and remove existing 50,000 welded steel tank and appurtenances
- Abandon Existing Stonegate Water Treatment Plant
- Fully demolish and remove existing Stonegate treatment plant
Questions shall be addressed to Rob Hillebrecht, Principal Engineer, at rob@sunnyslopewater.org
